Excavation Inspection Form

Excavation and Trenching Safety Checklist

Excavation Inspection Form. Web trench location/station and dimensions: Ladders placed no more than 25 feet apart.

Excavation and Trenching Safety Checklist
Excavation and Trenching Safety Checklist

Surface encumbrances supported or removed. Excavations and protective systems inspected by competent person daily, before start of work. This instruction establishes inspection procedures and provides clarification to ensure uniform enforcement of the excavation standards. An unprotected trench can be an early grave. Walkways and bridges over excavations 6' or more in depth are at least 20 inches wide and are equipped with required guardrails. Construction safety and health standards, subpart p., 29 cfr 1926.650, 651, and 652. Web daily excavation safety inspections are ideally conducted before shift starts and, as deemed necessary, during work. Is the depth of the cut more than 2’ below the bottom of the shield are walkways over the excavation at least 20” wide and 2’ past both edges are they equipped with guardrails? Ladders placed no more than 25 feet apart. Employees prohibited from working or walking under suspended loads.

Web spoils, materials, and equipment set back a minimum of 2' from edge of excavation. Employees prohibited from working or walking under suspended loads. Utilities 0 0 0 0 n/a 0 0 0 utility locates contacted at least 2 working days prior to start of digging, and appropriately marked and identified underground installations have been protected, supported, or removed when the excavation is open Is the depth of the cut more than 2’ below the bottom of the shield are walkways over the excavation at least 20” wide and 2’ past both edges are they equipped with guardrails? Surface encumbrances supported or removed. Web download free template. One cubic yard of soil can weigh as much as a car. Web daily excavation safety inspections are ideally conducted before shift starts and, as deemed necessary, during work. Employees protected from loose rock or soil. Web spoils, materials, and equipment set back a minimum of 2' from edge of excavation. This instruction establishes inspection procedures and provides clarification to ensure uniform enforcement of the excavation standards.